Zarichnyu. August
31.08.2022

In building 9, the entrance group is being arranged and finishing works are being carried out on the floors. Work is being carried out on the installation of aluminum structures on the 1st floor. Work is being carried out on the installation of facade insulation and installation of brackets for air conditioners. Work is being carried out on the installation of the roof. Work is being carried out on the installation and arrangement of engineering systems.

In building 8, work is being carried out on the installation of facade insulation and installation of brackets for air conditioners.

In building 7, work is being carried out on the installation of facade insulation and installation of brackets for air conditioners.

In building 7.1, work continues on the arrangement of internal engineering networks.

Landscaping work has begun.

View the photo report

   